Roadmap

Built in waves.
Proven at portfolio scale.

100MW operational across four NEM regions by month 36. Foundation portfolio already secured.

Wave 1
Months 1–6

Foundation Sites Secured

First hubs acquired in NSW and SA. Connections secured.

01
Wave 2
Months 7–12

Portfolio Velocity

One new site acquired every month. Equipment slots locked with HV equipment manufacturers.

02
Wave 3
Month 18

Revenue Begins

The first two hubs energise and begin trading. Eight hubs operational by month 24.

03
Wave 4
Month 36

The Next Wave

100MW operational across four NEM regions. Expansion pipeline, same playbook, proven at portfolio scale.

04
Watch — walkthrough
Foundation Portfolio

Sites secured across NSW & SA.

Bathurst
NSW
1.5MW
Port Wakefield
SA
2MW
Port Augusta
SA
3MW
Whyalla
SA
5MW